Customer Goal
New building composed of 2 production levels, for each production level there is two technical floors for HVAC and electricity. Ground floor will be used for other utilities, to finally make 7 floors building with a 5500mÂē footprint. Equipment will be implemented in two phases, approximatively one first phase for first production floor and a second one for second production floor.
Project data
- Faisability design – consumer list :
– more than 700kW for process
– more than 700kW for HVAC
– 300 kW ground floor utilities
– 1000 kW for lights and sockets”         Â
- Dynamic no break systems study (flywheels)
RK-TEC solution   Â
Faisability design:Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â
- Power balance and cabinet list
- evaluate number of no-breaks and low voltage switchboards
- Cost estimate for the whole electrical package (HV and LV)Â Â
Customer gain
- New building
- Increasing the production capacity